Saturday 12 May 2012

Countdown and.....lift-off!

VANCOUVER, BC (AP) - On Wednesday, just after 1:00pm, it happened: the crap shack took flight. After weeks of preparation, it finally happened. So I'll go back a few days to take you through the journey of the last little while...

I believe last time we left our heroes, they were facing a place that looked something like this. Filled with layers of stuff, asbestos, non-containing vermiculite (more on that), etc.and still needing a LOT of work, I continued to work evenings and weekends to transform the place from this:


To this...


To this...



However, in the process, (shock of all shocks), I found, you guessed it...MORE hazmat stuff...So, called up fleck and they came back to remove more vermiculite, more insulation, and even more asbestos-containing flooring that hadn't been picked up. It was mainly just sloppy work - they hadn't diligently gone through the house. So, they came back through and throughly vacuumed and got rid of "most" of it. I still had the vermiculite raining down upon me even after that (while removing some of cedar shakes that connected into the attic - yes, was wearing an approved respirator and other equipment), and on top of that, they had damaged the floor joists, broke a window, damaged piping...and on lift day, we found....MORE asbestos containing tape (on duct work)...so...they came back AGAIN...



The state of the cleanup, "post" cleanup... You can
see the vermiculite mixed into the grey insulation
A nice cut through our sub-floor (which extended into the joists)

I also spoke with Worksafe BC and after a lot of beauracratic bafflegag, the official line I got was this: unless you've sampled every speck of vemiculite (which would cost more to sample than to remove), Worksafe treats it as asbestos (to cover their arses). So, lesson is: vermiculite = asbestos (even if it it is the equivalent of potting soil). Awesome.

With the hazmat chapter NEARLY done (we still need to sort out payment and get our hazmat clearance certificate), I moved on to nail removal. A LOT of nail removal...my my rough estimation about 20,000 nails (a little over 1200 sq.ft. of wall, with on average about 16 nails per square foot). Probably the most challenging aspect of this was establishing and taking down the 21' high scaffolding by myself. The good news? (A) It's done, and (B) it trimmed 13 lbs off of me in the process with no injuries in the process aside from the odd nail poke and scratch (and a lot of sore muscles).


That left us with the this one the interior:

The other big job was getting four 5'x5' holes dug in the slab (the big block of concrete that is the "basement floor"), which differs from the foundation (which are basically the "concrete walls" that the weight of the house rests upon). James (one of the general trades people working on the site who will be assisting throughout) cut a line into the slab using a jackhammer, but we quickly realized that the slab was only about 1.5" thick, meaning that a 17 lb. sledge hammer did the job with no problem. Once we were through the slab, the digging began...and kept going...through a 3" organic layer, and then about 36" of thick clayish loam, before we hit water, and finally a clay lens (hard pan). If it's not already obvious, it was HEAVY work with VERY sticky soils that made for slow work. Furthermore, we found out that with 6-12" of standing water in the holes, we needed to add gravel, so that then got sorted. But, after several days of slogging soil and moving gravel, we were set with four holes, approved by Henry Hsu (our structural engineer from Formosa Engineering - who has been wonderful).

My what a lovely hole in the floor!
With things set to go, on Wednesday, May 9th, we obtained a permit from City Hall (they love their permits!) to block off half of the street, and brough in Zebiak for the lift. I arrived on site at 7:30am and met up with James and Mark (our site superintendent). We worked to finish up the lift prep (get the gravel level, pump out water that had built up in the holes), remove some boards, garbage, etc. etc. and we were set.





The crew of four guys from Zebiak arrived at around 8:30 and started setting up the "cribbing" (basically - jenga for houses). Each block is about 8" x 8" x 4' and weighs about 50 lbs. These are stacked up to near the ceiling and that took about 3 hours to get set. After that, they brought along a crane and unloaded the 30' steel beams (one of the two small hiccups of the day was that the house is 32' long - they "extend" the steel beams using cribbing...the other hiccup being the fact that we had originally said "about 4 feet" for the raise, not 4'9" which was the actual height...which we managed to sort in the end with an extra hour's work).

Here you can see the crane unloading the first of the beams
The beam ever-so-carefully being manoevred past the "prized" oak trees
on our street (seriously, the crane operator was an artist)
Here you can see the cribbing, a jack, the beam, and how it fits in with the existing ceiling joists.

With all of the pieces in place, around 13:00 Pacific Daylight Time, we had lift off! I barely even noticed it at first because they only took it up an inch or so, but eventually, they got things moving...and once the lift was underway it was pretty fast. They go up about 14" in a single "lift" which takes about 90 seconds, and then the add additional cribbing before resetting and repeating the process. Ultimately they did about 5 lifts and here was the result:







In the end, this was the change...


Pre-lift
Mid-lift

Post-lift

 I've got some video as well that I'll add soon, but for now I'll leave you with this as a parting shot - it gives you a good sense of how much the house is now UP in the air. 




No comments:

Post a Comment